First Baptist Church MAC Progress

Since the last update, the outside brick and metal have been all put up just in time for the cold, wintery season. The builders have now turned inside to finishing drywall and starting on the gym ceiling. A volunteer work team from Newfield, New York, came to help put up the furring strips and perforated sheet metal that goes on the MAC ceiling. The whole look of the building was drastically different when they left after just one week. Work teams are such a blessing to the ChurchCare Construction ministry. The missionary builders are usually encouraged by the progress and fellowship of the volunteers who give up their time to help. The builders are now making good progress on taping and mudding drywall after recently finishing hanging 800 sheets of drywall.